Special Districts > Crestline Sanitation District > History & Background
 

Seeley Creek Treatment Plant

The Seeley Creek WWTP is the second largest of the District's three treatment facilities with a design capacity of 0.5 mgd. This facility went through a major plant expansion in 1985 and, accordingly, it can be considered to be the newest of the three treatment plants. Seeley Creek was originally constructed in 1974 as a 0.20-mgd package activated sludge facility to treat flows from Assessment District No 5. The treatment system consisted of an in-ground circular tank containing an activated sludge aeration basin, secondary clarifier, chlorine contact chamber and digester.

As flow approached design capacity, the District constructed a 0.1 MG flow equalization basin in 1983. The flow equalization basin captured the peak flow and released it during low flow, thus extending the overall treatment capacity and efficiency of the treatment plant. This system served its purpose for the next two years leading up to the 1985 construction of a new 0.5-mgd facility. The new facility utilized a fixed film process (i.e., trickling filter) to provide secondary treatment followed by chlorine disinfection. This process allowed gravity flow, increased reliability and reduced operation and maintenance costs. Solids dewatering is accomplished at the Huston Creek WWTP. The existing 0.20-mgd package plant was converted into a primary clarifier as part of the 1985 construction. Effluent is discharged to the Seeley Creek gravity outfall system.

Flow Equalization - Wastewater first enters the treatment plant site immediately upstream of the 0.1 MG flow equalization basin. At this location, there is a bar rack and flow diversion structure. All wastewater first passes through this bar rack and is then routed into the equalization basin or main headworks structure. Under normal conditions, the equalization basin is bypassed and raw wastewater is sent directly to the main headworks structure. The flow equalization structure has not been used except during start-up and for emergency purposes, since construction of the plant upgrade in 1985.

Pretreatment - Raw wastewater flows from the upper bar rack into a second headworks located in the main headworks structure. This structure contains a bar rack, comminutor and Parshall Flume. Once through the bar rack, solids in the wastewater are shredded by the comminutor. Downstream of the comminutor, the Parshall Flume is utilized for measuring flows. Grit is removed by hand from a raised section of the headworks structure.

Primary Treatment - The 45-foot diameter primary clarifier has a side water depth of 12 feet. Although constructed from the original circular package plant, the overall design is virtually identical to that of a standard primary clarifier. Sludge from the secondary clarifier is pumped to the primary clarifier for co-settling with primary sludge. This combined sludge is then pumped into an adjacent concrete tank for temporary storage prior to being hauled to the Huston Creek WWTP. Primary skimmings accumulate in a sump prior to being pumped to the holding tank. Both sludge and skimmings pumping is accomplished by a single air-driven diaphragm pump. The sludge pumping cycle and duration are controlled via manually adjustable timers. Pumping of primary skimmings is accomplished manually.

Secondary Treatment - Primary effluent flows by gravity into a 45-foot diameter trickling filter containing 12 feet of stacked plastic (cross-flow) media. The filter is covered with an aluminum dome for temperature control and to keep leaves, pine needles and snow from clogging the filter. The trickling filter is operated in a constant recirculation mode. Two submersible centrifugal pumps provide recirculation. Both pumps are constant speed pumps and are duty units used in a lead-lag mode of operation.

Effluent from the trickling filter flows by gravity into a single secondary clarifier. The 36-foot diameter clarifier has a 14-foot side water depth. The clarifier has a center drive sludge rake and surface skimming mechanism. Secondary skimmings flow by gravity into a sump where they accumulate prior to being pumped to the primary clarifier. Secondary sludge pumping is accomplished through use of a single air-driven diaphragm pump. The pumping system is identical in design to that of the primary sludge pumping system. Accordingly, the pumping cycle and duration are controlled via manually adjustable timers. Pumping of secondary skimmings is performed manually.

Effluent Disinfection - Chlorine disinfection is accomplished in a concrete basin of serpentine design similar to the Huston Creek chlorine contact tank. Chlorine feed is flow-paced and also has a manual backup control. Chlorine dilution water is supplied by plant effluent. There are two manual wall mount chlorinators (one duty, one standby). Chlorine gas is supplied from a one-ton tank and a standby 150-pound cylinder. The system is the same as that described for Huston Creek.

Effluent Flow Metering - Plant flow is continuously recorded in the headworks via a sonic flow meter mechanism.

Solids Handling - As stated earlier, the Seeley Creek WWTP has no on-site sludge handling facility. All skimmings and solids are temporarily stored in the on-site sludge storage tank prior to being hauled to the Huston Creek WWTP for mechanical dewatering. Grit and screenings removed by hand are combined with the Huston Creek grit and hauled to an appropriate disposal site.

Plant Water - The treatment plant has a limited supply of fresh water which is supplied from a horizontal well that flows directly into the plants water system. A steel tank located on a hill above the equalization basin was originally designed to be refilled as necessary by tanker truck when the well supply is "dry."  This tank leaks badly and is unusable and therefore out of service.  Potable water is provided only at the operations building for drinking purposes.

Introduction | BACK | NEXT: Cleghorn Treatment Plant